Thursday, December 17, 2015

PMP - Project Management test answers of 2016.

Find Complete and recently updated Correct Question and answers of PMP - Project Management. All Answers updated regularly with new questions. Upwork PMP - Project Management test answers of 2016.



Question:* What is the definition of an SOW?

Answer: • Statement of Work

Question:* A Change Control Board is:

Answer: • A formal constituted group of stakeholders responsible for approving or rejecting changes to the project baselines

Question:* One of the members of your project team comes to you and says that he heard that one of the suppliers to the project had given a substantial gift to one of the project team members in hopes that the team member would favor his company with a purchase order. This team member then ordered the parts from this company. What should you do?

Answer: • Investigate the matter completely

Question:* What is "KPI"?

Answer: • Key Performance Indicator

Question:* Which is the BEST definition of quality?

Answer: • A product that satisfies all of the requirements of the people who pay for it.

Question:* What should the project manager do to ensure that all work is included in the project plan?

Answer: • Create a WBS

Question:* A project management triangle is a model of the constraints of project management.

Answer: • True

Question:* A project manager is reporting the final status of the closed contract to the stakeholders. Which form of communication is appropriate?

Answer: • Formal written

Question:* The Triple Constraint Model of a project consists of:

Answer: • Scope, Schedule, and Cost

Question:* What are the steps for defining the scope of a project?

Answer: • Define project objectives, goals, sub-phases, tasks, resources, budget, and schedule.

Question:* Which of the following is NOT a responsibility of a project manager?

Answer: • Sponsoring the project

Question:* Project scope is the part of project planning that involves determining and documenting a list of specific project goals, deliverable, tasks, and deadlines.

Answer: • True

Question:* A person who is involved in, has something to gain or lose, or may be affected by the activities of the project is called a:

Answer: • Stakeholder

Question:* Which one of these is part of the execution stage?

Answer: • All of these

Question:* The margin on the project you are working on is low, and it is extremely important that the cost estimates for the work to be accurate. While reviewing the cost estimates for it, you notice that one for an element in the WBS is 10% higher than two previous projects for very similar work. What should you do?

Answer: • Ask the person responsible for the estimate to explain the difference and bring supporting information to you

Question:* True or False? One side of the project management triangle cannot be changed without affecting the others.

Answer: • True

Question:* What must a project manager do to ensure clear boundaries for project completion?

Answer: • Complete a scope statement

Question:* What are the 5 basic Phases of Project Management

Answer: • Initiation, Planning, Execution, Control, and Close

Question:* What is the total float of a project?

Answer: • Amount of time a task can slip without affecting the project end-date

Question:* A contract to deliver has been signed for the current project you are working on. The customer who has signed the contract has telephoned you to request additional work to be done on the project, which will affect the budget, but not the schedule of the project. What should you do next?

Answer: • Respond to the customer’s request by explaining the change procedure and asking that he or she submit a request for change

Question:* What must a project manager do to create clear boundaries for project completion?

Answer: • Complete a scope statement

Question:* What is the purpose of a project charter?

Answer: • All of these

Question:* What happens at each gate when using the phase-gate model?

Answer: • Continuation of the project is reviewed by a committee

Question:* A type of project management that is typically used in technology and software development is:

Answer: • Agile project management

Question:* A group of related projects that are managed in a coordinated way that usually include an element of ongoing activity is called a:

Answer: • Program

Question:* What is WBS typically used for:

Answer: • Organizing and defining the total scope of the project

Question:* True or False? The closing stage of a project consists of 2 sub-stages?

Answer: • True

Question:* A temporary endeavor undertaken to create a new product or service is called a:

Answer: • Project

Question:* What is a management style that is used for breaking down projects into small components?

Answer: • Work breakdown structure

Question:* You are managing a project that is in process. A large and unexpected problem occurs that will cause a delay in the schedule in excess of the contingency schedule for the project. What should you do?

Answer: • Look at other tasks in the schedule and see which ones should be reduced to allow time for this problem to be worked out

Question:* The stakeholder analysis should be done in which stage of the project management?

Answer: • Initiation

Question:* Some members of your project team have come to you and asked that they be permitted to work on a flexible schedule. Others feel it is important that all team members be on site at all times unless they are absent for business reasons. What should you do?

Answer: • Arrange a meeting of the project team members and allow them to decide

Question:* Which of these is NOT one of the Five Performance Domains?

Answer: • Budgeting the project

Question:* Which of the following is an example of a conflict of interest?

Answer: • You are the owner of a company that is supplying parts to a project that you are managing

Question:* The original approved plan plus or minus approved scope changes is called the:

Answer: • Baseline

Question:* A project manager makes a narrative description of the work that must be done for her project. This is called a:

Answer: • Statement of work

Question:* A graphic display of cumulative costs, labor hours, percentage of work etc. plotted against time is known as:

Answer: • An S-Curve

Question:* What is the term for a histogram that shows how many results were generated by each identified cause?

Answer: • A Pareto Diagram

Question:* The process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement is called?

Answer: • Management by objectives

Question:* You are managing a design project. You find that bringing all of your team members into a single room to work increases their communication, and helps build a sense of community. This is referred to as a:

Answer: • War room

Question:* During the full life cycle of the project, a plot of the project’s expected expenditure will usually follow a characteristic “S” shape. This indicates that:

Answer: • The bulk of the project budget will be spent in the execution phase

Question:* Your manager wants you to prepare a presentation for him to present at a conference. Most of the material in the presentation will be facts that are the results of your project. He intends to present the material under his own name. Your name will not appear. What should you do?

Answer: • Meet with your manager’s manager and discuss the problem

Question:* What kind of a relationship is it when completion of a successor is dependent on initiation of its predecessor?

Answer: • SF (start-to-finish)

Question:* Which one of these is NOT a stage of the phase-gate model?

Answer: • Research

Question:* A control shows seven data points on a row on one side of the mean. What should be done?

Answer: • Find an assignable cause.

Question:* What are examples of project stakeholders?

Answer: • Project leader, project team members, upper management.

Question:* PRINCE2 focuses on:

Answer: • Controlled environments

Question:* Taking action to decrease the total project duration after analyzing a number of alternatives to determine how to get the maximum duration compression for the least cost is known as:

Answer: • Crashing

Question:* In a current project, you use earned value calculations to figure out that you’re going to run $500 over budget if the project continues at the current rate. Which of the following core characteristics of a project manager are you using to find the problem?

Answer: • Knowledge

Question:* How many phases are there in a phase-gate model?

Answer: • 6

Question:* Any numbering system that is used to monitor project costs by category such as labor, supplies, or materials is called a:

Answer: • Code of Accounts

Question:* What does "PRiSM" stand for?

Answer: • Projects Integrating Sustainable Methods

Question:* Which of the following is NOT a Project Management Knowledge Area?

Answer: • Initiating

Question:* As a direct result of the successful completion of a project, your manager approves a bonus of $25,000 for you. There are fifteen members of the project team. One of the people in the project team has been a very low contributor to the project; the other fourteen have all been above standard. What should you do with the money?

Answer: • Ask the team members how they would divide the money

Question:* You are managing a project and the customer’s engineer visits your facility on an inspection and general getting acquainted tour. During the tour they make the comment that the parts that are being designed should be in stainless steel instead of plain steel with enamel. What should you do?

Answer: • Speak to the visiting engineers and discuss having an informal meeting between your engineers and the visiting engineers

Question:* A project coordinator may typically be found in a ____________ organization

Answer: • Weak matrix

Question:* Managing projects that are uncertain and complex are often called:

Answer: • Extreme Project Management (XPM)

Question:* Outputs of the Plan Risk Responses process include:

Answer: • Residual risks, fallback plans, and contingency reserves

Question:* The focus on how time and resources are invested into making changes that people want to see happen is known as:

Answer: • Benefits Realisation Management

Question:* Your project management team includes two external consultants each from a different company. You found that repeated conflicts between the two consultants already slow down project progress and jeopardize achievement of objectives. Which stage of team development can be difficult to overcome in such a situation?

Answer: • Kickoff from Assignment, Kickoff, Training, Communicating

Question:* An unintended break in a network path, usually caused by missing activities or logical relationships, is called a:

Answer: • Hanger

Question:* An example of scope verification is:

Answer: • Reviewing the performance of an installed software module

Question:* Decomposing the major deliverables into smaller, more manageable components to provide better control is called:

Answer: • Scope definition

Question:* You hire a person from a competing company who has a great deal of expertise in your industry. During conversation with the person you determine that many of this person’s ideas were developed by the competing company. What do you do?

Answer: • Accept the new ideas

Question:* What is a risk owner?

Answer: • The person who makes a risk happen.

Question:* True or False? A hammock must have an internal sequence

Answer: • False



No comments:

HTML5 Upwork (oDesk) TEST ANSWERS 2022

HTML5 Upwork (oDesk) TEST ANSWERS 2022 Question: Which of the following is the best method to detect HTML5 Canvas support in web br...

Disqus for upwork test answers